Announcements

Hayfield Road Pipe Project: Truck Deliveries Dec 7, 14, 21
Hayfield Road Pipe Project Manager Dave Anglin sent the following information on December 4 along with apologies for the short notice. He will work with the contractor to make sure we receive as much notice as possible on any future activity that could disturb the neighborhood. The contractor (Garney) plans to receive pre-cast box culvert sections over the next three Saturdays (December 7, 14 and 21).
Those living along Hayfield Road may want to avoid parking on Hayfield Road on these three Saturdays from 7:00 AM to 5:00 PM or until the last of 12 tractor trailer flat-bed trucks leaves the neighborhood. There are two especially important areas to keep clear: (1) the south bound section where the pool property fronts along Hayfield Road to allow sufficient room for trucks to turn into the parking lot drive way; (2) it will also be helpful if the residents at 7815, 7817, and 7819 Hayfield Road will avoid parking on the street, if possible. The tractor trailer will need room to make the left turn out of the pool property onto Hayfield Road. It will be a tight turn even with the full northbound lane width open. Any cars parked in front of these homes will make that turn more difficult.
The culvert sections will arrive on tractor trailer flat-beds trucks. The reason they do this on Saturdays is due to manpower and safety. A 5-man crew is required to safely unload the culvert sections and that crew is usually busy with the sanitary main pipe work during the normal work week days. They will bring in a total of 12 trucks over a 10-hr workday. Each truck has 3 sections, and each section takes about 30 minutes to properly offload. The first delivery will be at 7:00 a.m. and we made it quite clear that they cannot enter the neighborhood prior to 7:00 a.m. (Unfortunately, the noise ordinance limits work prior to 9:00 a.m. only on Sunday and federal holidays.) The delivery trucks will be able to turn right down into the laydown area in the pool parking lot to off load and then depart. This is the first delivery set for the pre-cast culvert sections. The remaining culvert sections will not be ready until the end of January. Dave will provide as much advance notice about that schedule as possible.
Reminder about Replacement Trees / Hayfield Road Pipe Project
Mary Millikin, HCA Beautification Chair, wants to remind Hayfield Farm residents about the County’s requirement for replacement trees. To address any concerns about replacement trees for trees that are removed, the County is requiring the contractor to replant the same type of trees that they removed in the same places. Those trees include red maples, American hollies and redbuds. The “100% Design Plan for the Hayfield Road Pipe Conveyance System” dated July 9, 2018 specifies this on page 96.

December Hayfield News 2019
Check out the December Hayfield News. Included in this issue: Hayfield Road Pipe Conveyance System Update, Garden Club Clippings, Hayfield Happenings, etc.

Hayfield Road Pipe Project: Sanitary Main Installation – 11/19/2019


Hayfield Road Pipe Project: Preserve Two Trees; Remove One – 11/23/2019
Initially, the contractor asked to remove three maples in the median strip closest to the pool – see attached marked up aerial photo. The reasons for the request are the limbs overhanging the road posing a work impediment and associated limb damage from the excavators. Dave Anglin asked two Fairfax County Landscape Architects – one of whom is an Arborist – to inspect the trees and assess the request with the goal being to save the three trees and limit any tree work to pruning, if possible. The only two circumstances to consider removing any tree are if it:
- Were already in decline or dead; or
- Would otherwise not survive the impact of the necessary excavation to install the box culvert.
Dave is very aware that landscaping is very important to the community and is notifying us to avoid surprising anyone. Further, in this case, this additional removal is in the best interest of all parties. Please see the four pictures with this update.





Hayfield Road Pipe Project: 11/12/19
Hayfield Road Pipe Project Update 11/12/2019
I will answer by what the contractor’s schedule currently says and what I think based on what I’m seeing in the field.
As always–please keep in mind that weather factors can influence this project. Good weather is great, of course, but bad weather can delay projects as we all know.
According to the contractor’s schedule they will be installing sanitary sewer line in advance of the start of the box culvert installation through the middle of January, 2020.
7’x4’ box culvert installation, which for our purposes also includes the outlet structure and plunge pool, will begin in mid-January, 2020. They will also be performing small water line and water service relocations as the work on the box culvert progresses. The box culvert goes up past Broadmoor St. where it changes to 48” reinforced concrete pipe (RCP). The box culvert installation should be complete by May. Installation of the 48” pipe will continue after that. The remaining work in the area of the pool will consist of restoration and repaving. According to the schedule, milling and paving happens last in October 2020.
The contractor has indicated they plan to beat the project schedule. Keep in mind they also have a hard deadline to be out of the swim club lot of May 1. They want to have most of the project work complete, except for the Telegraph Road crossing and some restoration done by then as well.
As a practice, I don’t like to predict early finishes to construction projects. I think it’s reasonable to tell the property owner that the area in front of their house will be pretty well clear of construction by mid-April at the latest, very likely several weeks earlier. Again, keep in mind that bad weather usually impacts (delays) major construction projects.

November Hayfield News 2019
Check out the November Hayfield News. Included in this issue: Caroling for Cans, Hayfield Road Pipe Conveyance System Update, Hayfield Happenings, etc.
Recent Comments